Constance Baker Motley Recreation Center Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct the exterior facade and interior pool ceiling and locker room areas at Constance Baker Motley Recreation Center.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: April 2025
Projected Completion Date:
April 2027
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Constance Baker Motley Recreation Center, Manhattan
Located at 348 East 54th Street
Community Board: 06
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project
Last updated: 06/30/2025