Highland Park Dog Run Construction
-
100% complete
-
100% complete
-
12% complete
This project will construct a dog run in Highland Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date:
July 2023
Procurement
Start Date: July 2023
Projected Completion Date:
July 2024
Completion
Date:
February 2025
Construction
Start Date: March 2025
Projected Completion Date:
March 2026
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Highland Park, Queens
Western side of Lower Highland Park adjacent to Jamaica Avenue
Community Board: 05, 05
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project
Last updated: 06/30/2025