Park of the Americas Basketball Court Reconstruction
-
100% complete
-
100% complete
-
2% complete
This project will reconstruct the basketball court and adjacent entrance at Park of the Americas.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2022
Projected Completion Date:
July 2023
Completion Date:
August 2023
Procurement
Start Date: August 2023
Projected Completion Date:
August 2024
Completion
Date:
January 2025
Construction
Start Date: May 2025
Projected Completion Date:
May 2026
Understand how we build parks.
Funding
Funding Source: City Council
Location
Park Of The Americas, Queens
104th Street and 42nd Avenue
Community Board: 04
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project
Last updated: 06/30/2025