Woodtree Playground Basketball Courts Reconstruction
-
100% complete
-
100% complete
-
7% complete
This project will reconstruct the basketball courts at Woodtree Playground.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2021
Projected Completion Date:
December 2022
Completion Date:
March 2023
Procurement
Start Date: March 2023
Projected Completion Date:
March 2024
Completion
Date:
January 2025
Construction
Start Date: March 2025
Projected Completion Date:
March 2026
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Woodtree Playground, Queens
20th Avenue between 37th Street and 38th Street
Community Board: 01
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project
Last updated: 06/30/2025