Woodtree Playground Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    7% complete

This project will reconstruct the basketball courts at Woodtree Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2021
Projected Completion Date: December 2022
Completion Date: March 2023

Procurement

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: January 2025

Construction

Start Date: March 2025
Projected Completion Date: March 2026

Understand how we build parks.

Funding

Total Funding: $3,825,000
Funding Sources:
  • Borough President
  • City Council

Location

Woodtree Playground, Queens
20th Avenue between 37th Street and 38th Street
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project