Riverside Park 78th Street Ramp Reconstruction
-
100% complete
-
100% complete
-
19% complete
This project will reconstruct the ramp near 78th Street in Riverside Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2022
Projected Completion Date:
March 2023
Completion Date:
March 2023
Procurement
Start Date: March 2023
Projected Completion Date:
March 2024
Completion
Date:
February 2025
Construction
Start Date: April 2025
Projected Completion Date:
April 2026
Understand how we build parks.
Funding
Funding Source: City Council
Location
Riverside Park, Manhattan
Riverside Drive and West 78th Street
Community Board: 07, 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project