Haffen Park Pool Complex Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the pool complex at Haffen Park.

Project Notes

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2021
Projected Completion Date: October 2022
Completion Date: February 2023

Procurement

Start Date: February 2023
Projected Completion Date: April 2026
Adjusted Completion Date: March 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Haffen Park, Bronx
1814 Burke Avenue
Community Board: 12

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 06/30/2025