Gwen Ifill Park Public Restroom Building Construction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a public restroom building in Gwen Ifill Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2024
Projected Completion Date: April 2025
Adjusted Completion Date: August 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Gwen Ifill Park, Queens
129th Avenue at 176th Street
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 06/30/2025