Gwen Ifill Park Public Restroom Building Construction
-
30% complete
-
0% complete
-
0% complete
This project will construct a public restroom building in Gwen Ifill Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2024
Projected Completion Date:
April 2025
Adjusted Completion Date:
August 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Gwen Ifill Park, Queens
129th Avenue at 176th Street
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project
Last updated: 06/30/2025