Chief Dennis L. Devlin Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will reconstruct the passive seating and planting, construction of sidewalk, fencing, painted games and a spray shower at Chief Dennis L. Devlin Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2022
Projected Completion Date: March 2023
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: April 2025

Construction

Start Date: April 2025
Projected Completion Date: April 2026

Understand how we build parks.

Funding

Total Funding: $3,000,000
Funding Source: Mayoral

Location

Chief Dennis L. Devlin Park, Bronx
Ellis Avenue, Olmstead Avenue, and Cross Bronx Service Road North
Community Board: 09

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 06/30/2025