Boerum Park Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

The project will reconstruct Boerum Park.

Project Notes

Project Update: The project has entered procurement and is being reviewed and prepared for solicitation.

Project Timeline

Design

Assigned & Start Date: June 2023
Projected Completion Date: October 2024
Completion Date: October 2024

Procurement

Start Date: June 2025
Projected Completion Date: June 2026

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Boerum Park, Brooklyn
Warren, Smith, Hoyt & Baltic Streets
Community Board: 06

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project

Last updated: 06/30/2025