Old Stone House Addition Construction
-
90% complete
-
0% complete
-
0% complete
This project will construct an addition to the Old Stone House.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2023
Projected Completion Date:
November 2024
Adjusted Completion Date:
September 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Washington Park, Brooklyn
5th Avenue between 3rd and 4th Street
Community Board: 06
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project
Last updated: 06/30/2025