Dawson Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will reconstruct Dawson Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2022
Projected Completion Date: November 2023
Completion Date: November 2023

Procurement

Start Date: November 2023
Projected Completion Date: November 2024
Completion Date: January 2025

Construction

Start Date: April 2025
Projected Completion Date: April 2026

Understand how we build parks.

Funding

Total Funding: $2,839,000
Funding Source: Mayoral

Location

Dawson Playground, Bronx
Dawson Street and Rogers Place
Community Board: 02

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 06/30/2025