Flushing Meadows Corona Park Destination Greenways Meadow Lake Segment Construction
-
30% complete
-
0% complete
-
0% complete
This project will construct a greenway at Flushing Meadows Corona Park by Meadow Lake Creek.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2023
Projected Completion Date:
January 2025
Adjusted Completion Date:
February 2026
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
The pathway along Meadow Lake Road West and Meadow Lake Promenade in Flushing Meadows Corona Park between Meridian Road and Boathouse Bridge