Sara D. Roosevelt Park Reconstruction
-
80% complete
-
0% complete
-
0% complete
This project will reconstruct Lion's Gate Field, the Pit multipurpose play area, and the Hua Mei Bird Garden at Sara D. Roosevelt Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2023
Projected Completion Date:
March 2025
Adjusted Completion Date:
June 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
Sara D. Roosevelt Park, Manhattan
Delancey Street and Grand Street between Chrystie Street and Forsyth Street
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project
Last updated: 06/30/2025