Allen and Pike Street Malls Reconstruction Phase 2

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the Allen and Pike Street Malls (Phase 2).

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: April 2025
Adjusted Completion Date: October 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Allen Street Malls, Manhattan
Allen and Pike Street Malls between Hester Street and Madison Street
Community Board: 03

 