Brooklyn Street Tree Planting FY23 - Community Boards 7 & 10

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant new and replacement trees in Community Boards 7 & 10 in Brooklyn.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: March 2023
Completion Date: January 2023

Procurement

Start Date: January 2023
Projected Completion Date: October 2023
Completion Date: April 2025

Construction

Start Date: March 2025
Projected Completion Date: March 2026

Understand how we build parks.

Funding

Total Funding: $500,000
Funding Source: Mayoral

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 06/30/2025