Dr. Charles Drew Park Natural Turf Field Reconstruction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the natural turf fields, security lighting and sidewalks at Dr. Charles Drew Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2023
Projected Completion Date: April 2025
Adjusted Completion Date: July 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: City Council

Location

Dr. Charles R. Drew Park, Queens
139-05 116th Avenue
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 06/30/2025