Hutchinson River Parkway District 10 Headquarters Construction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a headquarters for Bronx M&O District 10 at Hutchinson River Parkway.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Assigned & Start Date: June 2024
Projected Completion Date: September 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Hutchinson River Parkway, Bronx
Hutchinson River Parkway East, Continental Avenue and East 197th Street
Community Board: 10, 11

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 06/30/2025