Barretto Point Park Shoreline Restoration
-
5% complete
-
0% complete
-
0% complete
This project will restore and plant shoreline in Barretto Point Park.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: May 2025
Projected Completion Date:
November 2026
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Barretto Point Park, Bronx
Between Viele Avenue and Ryawa Avenue on East River
Community Board: 02
Project Staff
Contact NYC Parks about this projectLast updated: 06/30/2025