Brooklyn Tree-Damaged Sidewalk Reconstruction FY23 Community Boards 1, 2, 6, 7, 10-14
-
100% complete
-
100% complete
-
11% complete
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 1, 2, 6, 7, 10, 11, 12, 13 and 14 in Brooklyn.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2023
Projected Completion Date:
December 2023
Completion Date:
June 2023
Procurement
Start Date: June 2023
Projected Completion Date:
May 2024
Completion
Date:
December 2024
Construction
Start Date: January 2025
Projected Completion Date:
January 2027
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Last updated: 06/30/2025