Bushwick Inlet Park Sewer Connection Construction
-
100% complete
-
100% complete
-
15% complete
This project will install a sewer connection in Bushwick Inlet Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2023
Projected Completion Date:
February 2024
Completion Date:
July 2023
Procurement
Start Date: July 2023
Projected Completion Date:
July 2024
Completion
Date:
January 2025
Construction
Start Date: May 2025
Projected Completion Date:
November 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bushwick Inlet Park, Brooklyn
Kent Avenue between N.12th and N.11th Streets
Community Board: 01
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project
Last updated: 06/30/2025