Travers Park Basketball Courts Reconstruction
-
80% complete
-
0% complete
-
0% complete
This Project will reconstruct the basketball courts at Travers Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2024
Projected Completion Date:
February 2025
Adjusted Completion Date:
July 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Travers Park, Queens
This project is located between Northern Boulevard, 34th Avenue, 77th and 79th Streets
Community Board: 03