Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
April 2024
Completion Date:
February 2024
Procurement
Start Date: February 2024
Projected Completion Date:
February 2025
Completion
Date:
February 2025
Construction
Start Date: March 2025
Projected Completion Date:
March 2026