Bronx & Manhattan Private Funding Tree Planting FY24

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will plant new and replacement trees in Bronx and Manhattan with private funding.

Project Notes

Project Update: The project has entered procurement and is being reviewed and prepared for solicitation.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: June 2024
Completion Date: March 2025

Procurement

Start Date: May 2025
Projected Completion Date: May 2026

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 06/30/2025