Clove Lakes Park Baseball Field 1 Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct natural clay infield at baseball field 1 in Clove Lakes Park to synthetic turf including drainage, fencing, water misting, the backstop, and bleachers. It will also reconstruct the outfield area with new grass.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: January 2025
Projected Completion Date:
April 2026
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Clove Lakes Park, Staten Island
Clove Road and Park Drive
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks about this project
Last updated: 06/30/2025