Wagner Houses Pool Complex Reconstruction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the pool facility.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Assigned & Start Date: November 2024
Projected Completion Date: January 2026

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Wagner Houses Pool, Manhattan
The east side of Second Avenue, between East 120th Street and East 121st Street.
Community Board: 11

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 06/30/2025