Wagner Houses Pool Complex Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct the pool facility.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: November 2024
Projected Completion Date:
January 2026
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Wagner Houses Pool, Manhattan
The east side of Second Avenue, between East 120th Street and East 121st Street.
Community Board: 11
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project
Last updated: 06/30/2025