Dyker Beach Park Bleachers Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct the bleachers at Dyker Beach Park.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: April 2025
Projected Completion Date:
April 2026
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Dyker Beach Park, Brooklyn
86th Street and Belt Parkway between 14th Avenue and 7th Avenue
Community Board: 10
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project
Last updated: 06/30/2025