Manhattan Community Garden Permeable Paver Installation

  • Design
    0% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will install permeable pavers.

Project Notes

Project Update: A meeting was held with stakeholders to discuss the scope of work for the project. Parks is now reviewing feedback from the meeting and the scope of work to determine the schedule for the project.

Project Timeline

Design

The average time for design is 9-14 months. The design timeline for this specific contract will be established once the project scope is determined.

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Locations

  • Brisas Del Caribe, Manhattan
    237 East 3rd Street between Avenue B & C
  • Allied Productions/Le Petit Versailles, Manhattan
    247 East 2nd Street
  • La Plaza Cultural, Manhattan
    East 8th Street between Avenue B & C
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 08/01/2025