Clove Lakes Park Pathway Reconstruction
-
100% complete
-
100% complete
-
60% complete
This project will reconstruct paths in Clove Lakes Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2023
Projected Completion Date:
November 2024
Completion Date:
October 2024
Procurement
Start Date: March 2024
Projected Completion Date:
August 2024
Completion
Date:
October 2024
Construction
Start Date: November 2024
Projected Completion Date:
November 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Clove Lakes Park, Staten Island
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project
Last updated: 06/30/2025