Pelham Bay Park Orchard Beach Nature Center Telecommunication Service Installation
-
100% complete
-
100% complete
-
100% complete
This project will install a telecommunication service to Orchard Beach Nature Center in Pelham Bay Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2024
Projected Completion Date:
October 2024
Completion Date:
October 2024
Procurement
Start Date: May 2024
Projected Completion Date:
October 2024
Completion
Date:
November 2024
Construction
Start Date: March 2025
Projected Completion Date:
July 2025
Completion Date: May 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Pelham Bay Park, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project
Last updated: 07/01/2025