John Paul Jones Park Pavement Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct pavement in John Paul Jones Park.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2024
Projected Completion Date:
June 2025
Completion Date:
June 2025
Procurement
Start Date: October 2024
Projected Completion Date:
March 2025
Completion
Date:
June 2025
Construction
Start Date: June 2025
Projected Completion Date:
December 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
John Paul Jones Park, Brooklyn
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project
Last updated: 06/30/2025