Hoyt Playground Ramp Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construction an accessible ramp at Hoyt Playground.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2024
Projected Completion Date: June 2025
Completion Date: June 2025

Procurement

Start Date: October 2024
Projected Completion Date: March 2025
Completion Date: June 2025

Construction

Start Date:

Understand how we build parks.

Funding

Total Funding: $350,000
Funding Source: Private

Location

Hoyt Playground, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project