Flushing Meadows Corona Park Garage Bay Entrance Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the entrance bay pavement at the Flushing Meadows Corona Park Garage.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2024
Projected Completion Date: June 2025
Completion Date: June 2025

Procurement

Start Date: October 2024
Projected Completion Date: March 2025
Completion Date: June 2025

Construction

Start Date:

Understand how we build parks.

Funding

Total Funding: $160,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 06/30/2025