Riverside Park Seawall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct a seawall along the Hudson River at West 97th Street in Riverside Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2024
Projected Completion Date: September 2025
Completion Date: March 2025

Procurement

Start Date: March 2025
Projected Completion Date: August 2025
Completion Date: April 2025

Construction

Start Date: April 2025
Projected Completion Date: August 2025
Completion Date: June 2025

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral