Fort Washington Park Retaining Wall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    5% complete

This project will reconstruct a retaining wall along Riverside Drive Service Road at West 161st Street in Fort Washington Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2024
Projected Completion Date: September 2025
Completion Date: April 2025

Procurement

Start Date: March 2025
Projected Completion Date: August 2025
Completion Date: June 2025

Construction

Start Date: June 2025
Projected Completion Date: December 2025

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Fort Washington Park, Manhattan

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 06/30/2025