Washington Market Park Plumbing Reconstruction
-
100% complete
-
100% complete
-
0% complete
This work will includes scope drainage lines, clearing existing drainage structures, replacing damaged drainage lines, and reconstructing lawn areas damaged during construction.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2023
Projected Completion Date:
June 2023
Completion Date:
May 2025
Procurement
Start Date: May 2025
Projected Completion Date:
October 2025
Completion
Date:
May 2025
Construction
Start Date:
Understand how we build parks.
Funding
Funding Source: City Council
Location
Washington Market Park, Manhattan
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project
Last updated: 06/30/2025