Owl Hollow Fields Sports Lighting Fixture Replacement
-
5% complete
-
0% complete
-
0% complete
The scope of work shall be for the installation of LED lighting systems for athletic facilities at various Parks & Recreation locations, Citywide. Work is to include but is not limited to the removal of the existing bulbs, the purchase and installation of LED sports lights, requisite mounting and wiring, and photometric surveys.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: January 2022
Projected Completion Date:
June 2023
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Freshkills Park, Staten Island
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project
Last updated: 06/30/2025