Owl Hollow Fields Sports Lighting Fixture Replacement

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

The scope of work shall be for the installation of LED lighting systems for athletic facilities at various Parks & Recreation locations, Citywide. Work is to include but is not limited to the removal of the existing bulbs, the purchase and installation of LED sports lights, requisite mounting and wiring, and photometric surveys.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: January 2022
Projected Completion Date: June 2023

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Freshkills Park, Staten Island

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 06/30/2025