Hendrick I. Lott House Interior Restoration
-
80% complete
-
0% complete
-
0% complete
This project will restore the interior of the Hendrick I. Lott House.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2023
Projected Completion Date:
January 2025
Adjusted Completion Date:
August 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Hendrick I. Lott House, Brooklyn
1940 East 36th Street
Community Board: 18
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project
Last updated: 06/30/2025