Hendrick I. Lott House Interior Restoration

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will restore the interior of the Hendrick I. Lott House.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2023
Projected Completion Date: January 2025
Adjusted Completion Date: August 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

Hendrick I. Lott House, Brooklyn
1940 East 36th Street
Community Board: 18

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project

Last updated: 06/30/2025