Mannahatta Park Reconstruction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct Mannahatta Park.
Project Notes
Project Update: Design is complete and permitting and legal review of the contract are in progress.
Project Timeline
Design
Assigned & Start Date: June 2024
Projected Completion Date:
May 2025
Completion Date:
May 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Mannahatta Park, Manhattan
Wall Street Between Water and South Streets
Community Board: 01
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project
Last updated: 06/30/2025