Inwood Hill Park Ballfields 1, 2 & 4 Reconstruction and Ballfield 1 Lighting Installation
-
100% complete
-
100% complete
-
28% complete
This project will reconstruct ballfields 1, 2 and 4 and install new lighting in ballfield 1 at Inwood Hill Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2020
Projected Completion Date:
January 2021
Completion Date:
October 2022
Procurement
Start Date: October 2022
Projected Completion Date:
July 2023
Completion
Date:
January 2025
Construction
Start Date: March 2025
Projected Completion Date:
March 2026
Understand how we build parks.
Funding
Funding Source: City Council
Location
Inwood Hill Park, Manhattan
Seaman Avenue and Isham Street
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project
Last updated: 06/30/2025