Red Hook Recreation Center and Pool Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct Red Hook Recreation Center and Pool, including systems and areas of the facility damaged by Hurricane Sandy, hazard mitigation, building electrification and sustainability upgrades, interior upgrades throughout the facility to comply with current building codes, and exterior upgrades to the building and pool.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: June 2025
Projected Completion Date:
June 2027
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Red Hook Recreation Area, Brooklyn
155 Bay Street
Community Board: 06
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project
Last updated: 06/30/2025