Woodlawn Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    1% complete

This project will reconstruct the public restroom building in Woodlawn Playground in Van Cortlandt Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2019
Projected Completion Date: January 2020
Completion Date: May 2020

Procurement

Start Date: May 2020
Projected Completion Date: February 2021
Completion Date: March 2024

Construction

Start Date: June 2025
Projected Completion Date: December 2026

Understand how we build parks.

Funding

Total Funding: $1,794,000
Funding Sources:
  • City Council
  • Mayoral

Location

Van Cortlandt Park, Bronx
Van Cortlandt Park East between Oneida Avenue and Kepler Avenue
Community Board: 07, 08, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 06/30/2025