Bartow-Pell Mansion Museum Structural Stabilization and Interior Reconstruction
-
35% complete
-
0% complete
-
0% complete
This project will stabilize and reconstruct portions of the interiors at the Bartow-Pell Mansion Museum in Pelham Bay Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2024
Projected Completion Date:
August 2025
Adjusted Completion Date:
April 2026
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
- State
Location
Pelham Bay Park, Bronx
895 Shore Road
Community Board: 10, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks about this project
Last updated: 06/30/2025