Space Time Playground Synthetic Turf Field and Basketball Courts Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct a synthetic turf field and reconstruct two basketball courts at Space Time Playground, including green infrastructure to capture storm water and new trees, benches, fencing, pavements, bleachers, water supply and drainage.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: June 2021
Completion Date: September 2023

Procurement

Start Date: September 2023
Projected Completion Date: September 2024
Completion Date: May 2025

Construction

Start Date: August 2025
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: $6,630,000
Funding Source: City Council

Location

Space Time Playground, Bronx
Lafayette Avenue between Bolton and Underhill Avenues
Community Board: 09

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project