Kimlau Square Arch Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the arch in Kimlau Square.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2021
Projected Completion Date:
August 2022
Completion Date:
September 2022
Procurement
Start Date: September 2022
Projected Completion Date:
June 2023
Completion
Date:
May 2025
Construction
Start Date: July 2025
Projected Completion Date:
July 2026
Understand how we build parks.
Funding
Funding Source: City Council
Location
Kimlau Square, Manhattan
Chatham Sq., Oliver St. and East Broadway
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project
Last updated: 07/01/2025