South Rochdale Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the basketball courts, multipurpose play area, and children's play area at South Rochdale Playground.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2022
Projected Completion Date: September 2023
Completion Date: February 2024

Procurement

Start Date: February 2024
Projected Completion Date: February 2025
Completion Date: April 2025

Construction

Start Date: June 2025
Projected Completion Date: June 2026

Understand how we build parks.

Funding

Total Funding: $5,850,000
Funding Source: City Council

Location

South Rochdale Playground, Queens
134th Road and 173rd Street
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 06/30/2025