Citywide Services Shops Elevator Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the elevator at the Citywide Services Shops.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2021
Projected Completion Date:
July 2021
Completion Date:
August 2023
Procurement
Start Date: August 2023
Projected Completion Date:
April 2022
Completion
Date:
May 2025
Construction
Start Date: September 2025
Projected Completion Date:
September 2026
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
850 East 138th Street
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project
Last updated: 06/30/2025