Greencroft Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the playground area at Greencroft Playground.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2021
Projected Completion Date: November 2022
Completion Date: September 2023

Procurement

Start Date: September 2023
Projected Completion Date: September 2024
Completion Date: April 2020

Construction

Start Date: June 2025
Projected Completion Date: June 2026

Understand how we build parks.

Funding

Total Funding: $8,400,000
Funding Sources:
  • City Council
  • Mayoral

Location

Greencroft Playground, Staten Island
Redgrave Avenue and Greencroft Avenue
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 06/30/2025